Define the sign convention
In this lesson, actual minus budget is the signed variance. A positive cost variance means overspending and is adverse. A positive revenue variance means revenue exceeded plan and is favourable. Always state the convention because reports may use the opposite sign.
Use the budget as the reference
To express overspend as a percentage of budget, divide the excess by the budget, not by the actual cost. For a remaining budget, subtract total spending to date from the authorised total.
Keep periods consistent
A monthly actual cannot be compared directly with an annual budget without an allocation assumption. If an annual plan is evenly allocated, a quarter represents one fourth; if it is seasonal, the question must provide the period allocation.
Separate price and quantity
When a purchase cost changes, both unit price and quantity may contribute. A simple price comparison holds quantity constant. Total spending alone does not show which driver changed, so avoid attributing an overspend without the necessary figures.
Build a reconciliation
List individual category differences and check that they sum to the total difference. Savings in one category can offset overspending in another. The exercises use hypothetical business budgets and explicit assumptions so the task is numerical interpretation rather than accounting policy.
Your first practice session
Signed variance means actual minus budget in this set. For costs, overspending is adverse. For revenue, exceeding budget is favourable. Use the budget as the percentage base.
Worked examples
-
1. A cost budget is $8,000 and actual cost is $8,600. What is the signed variance?
- +$600
- +$7,400
- +$16,600
- -$600
Reference:
q-2d5f2b5d-80· Report this questionShow answer and solution
Answer: A. +$600
Actual minus budget is 8,600 minus 8,000 = +$600, an adverse cost variance. -
2. Actual cost is $9,200 against a $10,000 budget. How far below budget is the cost as a percentage of budget?
- 92%
- 8%
- 8.70%
- 10%
Reference:
q-d31e24fa-108· Report this questionShow answer and solution
Answer: B. 8%
The saving is $800. Divide by the $10,000 budget: 8% below budget. -
3. An annual budget of $48,000 is allocated evenly by month. What is the first-quarter budget?
- $4,000
- $8,000
- $12,000
- $16,000
Reference:
q-7a7697f2-92· Report this questionShow answer and solution
Answer: C. $12,000
A quarter contains three of twelve months. 48,000 times 3/12 = $12,000.