Instructions for this set
Signed variance means actual minus budget in this set. For costs, overspending is adverse. For revenue, exceeding budget is favourable. Use the budget as the percentage base.
Feedback mode has no time limit or negative marking. The optional timed challenge allows 15 minutes and uses the scoring shown on its rules screen. Those settings are not official assessment rules.
-
1. A cost budget is $8,000 and actual cost is $8,600. What is the signed variance?
- +$600
- +$7,400
- +$16,600
- -$600
Reference:
q-2d5f2b5d-80· Report this questionShow answer and solution
Answer: A. +$600
Actual minus budget is 8,600 minus 8,000 = +$600, an adverse cost variance. -
2. Actual cost is $9,200 against a $10,000 budget. How far below budget is the cost as a percentage of budget?
- 92%
- 8%
- 8.70%
- 10%
Reference:
q-d31e24fa-108· Report this questionShow answer and solution
Answer: B. 8%
The saving is $800. Divide by the $10,000 budget: 8% below budget. -
3. An annual budget of $48,000 is allocated evenly by month. What is the first-quarter budget?
- $4,000
- $8,000
- $12,000
- $16,000
Reference:
q-7a7697f2-92· Report this questionShow answer and solution
Answer: C. $12,000
A quarter contains three of twelve months. 48,000 times 3/12 = $12,000. -
4. An annual budget is $24,000. Spending so far is $5,600, $6,200 and $4,800 across three quarters. What remains?
- $8,000
- $6,400
- $7,200
- $7,400
Reference:
q-b4009b0f-111· Report this questionShow answer and solution
Answer: D. $7,400
Spent total is $16,600. Remaining budget is 24,000 minus 16,600 = $7,400. -
5. Revenue budget is $50,000 and actual revenue is $54,000. What is the variance classification?
- $4,000 favourable
- $54,000 favourable
- No variance
- $4,000 adverse
Reference:
q-c0a04e7e-94· Report this questionShow answer and solution
Answer: A. $4,000 favourable
Revenue exceeded budget by $4,000, so the revenue variance is favourable under the stated convention. -
6. Travel is $500 over budget and software is $300 under budget. What is the combined cost variance?
- $800 over
- $200 over
- $200 under
- $800 under
Reference:
q-fcf9f620-98· Report this questionShow answer and solution
Answer: B. $200 over
Offset the $300 saving against the $500 excess to obtain a net $200 overspend. -
7. A plan budgets 200 units at $15 each. Actual purchase is also 200 units at $16 each. What is the excess total cost?
- $400
- $100
- $200
- $300
Reference:
q-413230a6-116· Report this questionShow answer and solution
Answer: C. $200
Holding quantity constant, the $1 extra per unit applies to 200 units, giving $200. -
8. A cost of $6,300 is 5% above budget. What was the budget?
- $6,150
- $6,615
- $5,985
- $6,000
Reference:
q-5247699d-58· Report this questionShow answer and solution
Answer: D. $6,000
Actual is 1.05 times budget. Divide 6,300 by 1.05 to get $6,000. -
9. A project has $15,000 authorised. It has spent $9,800 and has confirmed remaining costs of $6,100. What additional budget is needed to cover those costs?
- $900
- $1,100
- $500
- $800
Reference:
q-1bf0b678-154· Report this questionShow answer and solution
Answer: A. $900
Total expected cost is 9,800 plus 6,100 = $15,900. This is $900 above the authorised budget. -
10. An evenly allocated six-month budget is $30,000. After two months, actual spending is $11,000. Compared with the two-month allocation, what is the variance?
- $19,000 under
- $1,000 over
- $1,000 under
- $4,000 over
Reference:
q-36b56dc8-157· Report this questionShow answer and solution
Answer: B. $1,000 over
Two months receive 30,000 times 2/6 = $10,000. Actual $11,000 exceeds it by $1,000.
Review your method
Return to the budget variance reasoning lesson and identify the reasoning step behind each mistake before repeating the set.