General instructions for the test
- The set has 10 questions. The configured time limit is 15 minutes. The timer starts after you confirm the rules.
- The question palette on the right of the screen shows the status of each question, using these symbols:
- 1 You have not visited the question yet.
- 2 You have not answered the question.
- 3 You have answered the question.
- 4 You have not answered the question, but have marked it for review.
- 5 You have answered the question and marked it for review. It will be considered for evaluation.
- Click a question number in the palette to go to that question directly. Note that this does not save your answer to the current question.
- Click Save & Next to save your answer to the current question and go to the next one. Click Mark for Review & Next to save your answer, mark the question for review and go to the next one.
- To change your answer, select another option. To remove it, click Clear Response.
- For section navigation, calculator permission and scoring, use the rules shown before this particular set. They may differ between sets and from an official assessment.
- Scoring is shown before you begin. Unanswered questions carry no penalty. Feedback mode has no time limit or negative marking.
- Click Submit when you have finished. Your report then shows every answer, its solution and the time you spent on each question.
Practice mode has no clock and no negative marking; the answer and solution appear as soon as you choose an option.
Time and Work Test 1: questions and answers
Take the test first if you want an honest score. The answers and solutions below are folded away until you open them.
-
1. A can do a piece of work in 40 days and B can do it in 60 days. In how many days will they finish it working together?
- 24 days
- 50 days
- 21 days
- 26 days
Reference:
q-8ef27f1a-119· Report this questionShow answer and solution
Answer: A. 24 days
One day's work together = 1/40 + 1/60 = 1/24. They finish in 24 days. -
2. A and B together can finish a work in 5 days. A alone can finish it in 30 days. In how many days can B alone finish it?
- 10 days
- 25 days
- 2 days
- 6 days
Reference:
q-a9acf083-120· Report this questionShow answer and solution
Answer: D. 6 days
B's one day's work = 1/5 − 1/30 = 1/6. B alone takes 6 days. -
3. A, B and C can complete a work in 18, 36 and 12 days respectively. In how many days will they complete it working together?
- 9 days
- 5 days
- 3 days
- 6 days
Reference:
q-23f675f3-124· Report this questionShow answer and solution
Answer: D. 6 days
One day's work together = 1/18 + 1/36 + 1/12 = 1/6. They take 6 days. -
4. 6 men can complete a work in 24 days. In how many days can 16 men complete the same work?
- 3 days
- 64 days
- 9 days
- 15 days
Reference:
q-2a463450-90· Report this questionShow answer and solution
Answer: C. 9 days
Total work = 6 × 24 = 144 man-days. 16 men need 144 / 16 = 9 days. -
5. A can do a work in 10 days and B in 30 days. A works alone for 5 days and then leaves. In how many days will B finish the remaining work?
- 21 days
- 15 days
- 25 days
- 17 days
Reference:
q-59c59a64-138· Report this questionShow answer and solution
Answer: B. 15 days
A completes 5/10 = 1/2 of the work. Remaining = 1/2. B needs 30 × 1/2 = 15 days. -
6. A can do a piece of work in 20 days and B can do it in 5 days. In how many days will they finish it working together?
- 1 days
- 12.5 days
- 4 days
- 6 days
Reference:
q-81ffec53-118· Report this questionShow answer and solution
Answer: C. 4 days
One day's work together = 1/20 + 1/5 = 1/4. They finish in 4 days. -
7. A and B together can finish a work in 12 days. A alone can finish it in 20 days. In how many days can B alone finish it?
- 30 days
- 8 days
- 33 days
- 36 days
Reference:
q-7c4d1774-121· Report this questionShow answer and solution
Answer: A. 30 days
B's one day's work = 1/12 − 1/20 = 1/30. B alone takes 30 days. -
8. A, B and C can complete a work in 12, 20 and 30 days respectively. In how many days will they complete it working together?
- 3 days
- 5 days
- 4 days
- 6 days
Reference:
q-fea44b0c-124· Report this questionShow answer and solution
Answer: D. 6 days
One day's work together = 1/12 + 1/20 + 1/30 = 1/6. They take 6 days. -
9. 15 men can complete a work in 8 days. In how many days can 4 men complete the same work?
- 31 days
- 30 days
- 2.13 days
- 28 days
Reference:
q-101a2ca3-89· Report this questionShow answer and solution
Answer: B. 30 days
Total work = 15 × 8 = 120 man-days. 4 men need 120 / 4 = 30 days. -
10. A can do a work in 30 days and B in 12 days. A works alone for 10 days and then leaves. In how many days will B finish the remaining work?
- 4 days
- 12 days
- 2 days
- 8 days
Reference:
q-93497f0e-139· Report this questionShow answer and solution
Answer: D. 8 days
A completes 10/30 = 1/3 of the work. Remaining = 2/3. B needs 12 × 2/3 = 8 days.